Question 1
A project team decides to use two vendors instead of one for a critical component, so if one vendor fails, the other can deliver. This strategy BEST represents:
Show answer & explanation
Correct answer: B - Mitigation through redundancy
10 free, exam-style PMI Risk Management Professional (PMI-RMP) practice questions with answers and explanations. No signup required. Work through them below, then take the full free PMI-RMP practice test to study every exam domain.
A project team decides to use two vendors instead of one for a critical component, so if one vendor fails, the other can deliver. This strategy BEST represents:
Correct answer: B - Mitigation through redundancy
The CRITICAL difference between secondary risk and residual risk is:
Correct answer: A - Secondary risk is a NEW risk from implementing a response; residual risk is REMAINING exposure after response
A project has three identified risks: Threat A (40% × $150K = -$60K), Threat B (20% × $300K = -$60K), and Opportunity C (50% × $80K = +$40K). The total project EMV is:
Correct answer: B - -$80,000
A project assumes that: (1) the API specification will be finalized by March 1, (2) development can start immediately after specification, and (3) testing requires the completed development. If assumption #1 fails and the specification is delayed 6 weeks, the cascade effect is:
Correct answer: C - A cascade delay affecting specification, development, and testing sequentially
A project's SPI has declined over 4 consecutive periods: 1.02, 0.98, 0.93, 0.87. The risk manager should:
Correct answer: A - Flag the accelerating schedule deterioration as a critical risk and recommend corrective action
Which of the following is a correctly formed risk statement using the condition-cause-effect format?
Correct answer: C - Because of inexperienced team, integration testing may reveal defects, delaying the project
Three key stakeholders have different risk appetites: the sponsor wants aggressive innovation (high appetite), the compliance officer requires conservative approaches (low appetite), and the customer wants on-time delivery above all (moderate appetite). The risk manager should:
Correct answer: B - Facilitate a discussion to align on agreed thresholds per dimension, documenting trade-offs and gaining formal agreement
A risk manager evaluates three possible response strategies for a high-priority threat. Strategy A costs $40K and reduces risk exposure by $200K. Strategy B costs $80K and reduces exposure by $250K. Strategy C costs $150K and reduces exposure by $260K. Which offers the BEST value?
Correct answer: B - Strategy A because it has the most efficient cost-to-benefit ratio
A risk manager monitors the ratio of actual contingency used versus the proportion of project completed. At 50% project completion, 70% of contingency has been consumed. This ratio indicates:
Correct answer: B - Contingency is being consumed faster than project progress
During qualitative analysis, a risk is assessed as having very low probability (1) but catastrophic impact (5), giving a score of 5 - placing it in the Green zone. The risk manager should:
Correct answer: C - Override the matrix using professional judgment for catastrophic risks
Practice hundreds more PMI-RMP questions with instant scoring, weak-area drills, and full exam simulations.